Buying crusher software is the easy part. The hard part is the first month: setting up parties and products, connecting the weighbridge, training operators who have used a ticket book for years, and switching over without stopping dispatch for a day.
Most failed rollouts fail for the same reasons. Opening balances are wrong, the weighbridge connection is tested only on the go-live morning, and the operator is trained once and left alone. This 30-day plan avoids those traps. If you are still choosing a vendor, start with our buyer’s checklist.
Before day 1: pick a go-live date and an owner
- Go-live date: the first day of a month is best, so the old and new systems split cleanly at a month end.
- A project owner at the plant: one person, usually the manager or accountant, who has authority to make decisions and time to spend on it.
- A slow week if possible: avoid going live in the peak season or just before a large order.
Week 1: masters and opening balances
- Products with HSN code and GST rate, confirmed by your CA. Our note on GST for crushed stone and M-sand covers the common codes.
- Parties with GSTIN, address, credit limit and credit days. Clean up duplicates now; the same builder under three names will cause trouble for years.
- Vehicles, own and regular hired, with registration number and a fresh tare.
- Price list and rate contracts, set up as described in our post on rate contracts.
- Opening balances: party dues, stock by product, royalty balance against the sanctioned quantity, and ledger balances from your accountant.
Opening party balances are the most important item. If a customer’s balance is wrong on day one, every statement you send will be argued with.
Week 2: weighbridge and users
- Connect the weighbridge indicator and test it with known loads: an empty vehicle, a loaded vehicle, and a reweigh of the same vehicle.
- Check that the weight cannot be typed in and that the slip prints correctly on your printer and paper.
- Set up the internet backup: what happens when the connection drops, and how entries sync later.
- Create users with the right roles. Our post on user roles and audit trails covers the setup.
- Confirm that the weighbridge’s legal metrology verification is current. Software records what the scale says; it cannot correct a scale that is out of calibration.
Week 3: training and a parallel run
Train each group on its own work only, at the plant, in the language staff use every day:
| Group | What they learn | Time needed |
|---|---|---|
| Weighbridge operators | Weighment, slip, party and product selection, what to do when the internet drops | Two short sessions plus practice |
| Supervisors | Production, downtime, diesel, store issues, approving exceptions | One session |
| Accounts | Receipts, payments, GST reports, royalty reports, month end | Two sessions |
| Owner | Dashboard, daily report, exception review | One short session |
Then run old and new side by side for at least three or four working days. Every truck is weighed once, and the slip is recorded in both systems. At the end of each day, compare tonnes, values and slip counts. Differences found now are cheap to fix.
Week 4: go-live and support
- Close the old system at month end and carry closing balances into the new one.
- Go live on the first day of the month with the vendor’s support person at the plant, or on call, for the first few days.
- Check the first day’s dispatch report, invoices and royalty entries with the accountant before the next morning.
- Keep the old ticket book for emergencies only, and enter any manual slip into the system the same day.
- Review the first week’s exceptions with the owner.
After go-live: the first month end
The first month end is the real test. Plan an extra day for it, with the vendor’s help. Our post on the month-end close for a crusher plant sets out the steps. By the second month end, it should be faster than before.
Frequently asked questions
Do we need to move old years’ data?
Usually not. Bring opening balances and open invoices, and keep old records in the old system or in exported files for reference. Moving years of history adds cost and rarely adds value.
What if an operator cannot use a computer?
Most can learn the weighbridge screen in a few days, because it is a short, repetitive task. Pair a slower learner with a confident one during the parallel run.
Where this fits