At many crushers, the price on an invoice is decided by whoever is at the weighbridge. The operator remembers that one builder gets a special rate, another contractor gets free delivery up to a certain distance, and the RMC plant’s rate changed last month. Most days this works. On the days it does not, the plant either undercharges and loses money, or overcharges and starts an argument that delays payment.
This post shows how to set up price lists and rate contracts so the right rate reaches every dispatch automatically.
Three layers of pricing
Almost every crusher’s pricing can be described with three layers, applied in order:
- The standard price list: a rate per tonne or per load for each product at the plant gate, with a date from which it applies.
- Party rate contracts: an agreed rate for a particular customer, product and period, often with a committed quantity.
- Site or delivery rates: a freight-inclusive rate for delivery to a named site, or a freight charge by distance band.
When a truck is weighed, the software should look for a party contract first, then fall back to the standard price list, and add freight for delivered loads. The operator chooses the party, product and delivery site. The price follows.
What a rate contract should record
| Field | Why it matters |
|---|---|
| Party and GSTIN | The contract applies only to this customer |
| Product and unit | Rate per tonne, per brass or per load must be clear |
| Rate, and whether GST is extra | Avoids the most common billing argument |
| Valid from and to | Old rates should stop on their own |
| Committed quantity | Lets you track whether the discount is being earned |
| Delivery site and freight terms | Ex-plant or delivered, and to where |
| Credit days | Ties into the party’s credit limit |
| Approved by | Only the owner or sales head should create a special rate |
Units: tonne, brass and load
Sales may be priced per tonne, per brass (100 cubic feet, common in parts of Maharashtra and Karnataka) or per load. The weighbridge gives you tonnes. If you sell by brass or load, fix a conversion for each product and use it consistently, and print both the weight and the billed quantity on the slip. Customers accept a conversion they can see; they argue about one they cannot.
Freight-inclusive rates
Delivered pricing is where margins leak most often. A few rules help:
- Set freight by distance band or by named site, not by the driver’s estimate.
- Keep freight as a separate line on the invoice where your CA advises it, so the material rate stays comparable across customers.
- Match freight charged with freight paid to hired trucks every month. Our note on vehicle and freight settlement covers the payment side.
Ask your CA how GST applies to freight on your invoices, because the answer depends on how the supply and transport are arranged.
Changing prices without confusion
- Enter the new price list with a start date, before the date arrives.
- Let the old list end on its own; do not overwrite it, so old invoices still show the rate that applied.
- Send customers the new rates in writing before the change.
- Review all party contracts that expire in the next month, and renew or let them lapse deliberately.
Controls that stop leakage
- No rate editing at the weighbridge. If a rate is wrong, the operator flags it and a supervisor corrects the contract.
- A weekly report of dispatches billed below the standard list, by party, with the contract that allowed it.
- Committed quantity against actual for each contract, so a party that took a discount for a large order but lifted a small one can be spoken to.
Frequently asked questions
Should cash customers get a different price?
Many plants charge walk-in cash buyers the standard list and give credit customers contract rates. Whatever you choose, put it in the price list rather than leaving it to the operator.
How do we handle a rate dispute after dispatch?
Issue a credit or debit note against the original invoice rather than editing the invoice. That keeps your GST records and the party ledger clean. Our post on GST invoices for crushed stone covers invoice fields.
Where this fits